A federal judge ruled in late July that the Bureau of Reclamation and other
agencies violated the Endangered Species Act by approving 25-year contracts
for water diverted from the San Joaquin River at Friant Dam.
In his 78 page ruling, Judge Lawrence Karlton of the U.S. District Court in
Sacramento determined that the federal government failed to adequately
assess the impacts of the contracts on endangered salmon and other
threatened fish and wildlife, accusing the federal government of "arbitrary
and capricious conduct."
The contracts continue to leave 60 miles of the river, once a key
contributor to the state's ocean salmon fisheries, dry, dusty and lifeless
most of the year. Hopefully, the judge's decision will compel the agencies
to reverse years of ecosystem destruction and let the river flow once again.
The Bureau's decision to sign long-term contacts perpetuated the
environmental disaster that occurred after Friant Dam was finished in the
late 1940's. The diversion of the river resulted in the extermination of the
historically large and vibrant San Joaquin River spring chinook run that
ascended the Sierra Nevada before Friant Dam blocked upstream migration.
Five decades of dewatering of the San Joaquin, combined with federal and
state diversions from other San Joaquin tributaries and the Sacramento
system, have culminated in the Delta food chain crash that state and federal
scientists have documented over the past three years.
Karlton cited numerous violations of the law by three federal agencies - the
Bureau of Reclamation, U.S. Fish and Wildlife Service and the National
Marine Fisheries Service.
"While numerous examples may be found, perhaps the clearest example of
arbitrary conduct was when the Bureau, knowing that the Fish and Wildlife
Service bases its analysis on the full contract amount, nevertheless,
adopted a no jeopardy finding," said Karlton. "Because the Bureau failed to
carry out its duty to ensure against jeopardy and adverse modification, and
because the Bureau knew of the deficiency, the court must conclude that its
conduct was arbitrary and capricious."
Karlton, in a previous ruling last fall, determined that the signing of the
contracts violated the state Fish and Game codes, including the section
(5939) requiring dam operators to release enough waters below dams to keep
the fisheries in "good condition."
The case, NRDC v. Rodgers, is a 17-year-old case challenging Bureau of
Reclamation operations at Friant Dam. Earlier in the case, a unanimous panel
of the Ninth Circuit Court of Appeals in San Francisco invalidated previous
long-tern contracts for violating the ESA, forcing the Bureau to continue
water deliveries to Friant farmers under short-term contacts while new
environmental review were undertaken.
"This ruling documents the government's utter failure to consider the
wide-ranging impacts of Friant diversions on downstream fisheries and the
San Francisco Bay Delta," said Kate Poole, a senior attorney with the
Natural Resources Defense Council, who argued the case for a coalition of 14
fishing and conservation groups.
The plaintiffs include Trout Unlimited, California Striped Bass Association,
National Audubon Society, Stanislaus Audubon Society, California
Sportfishing Protection Alliance, United Anglers of California, California
Trout, Pacific Coast Federation of Fishermen's Associations, Sierra Club,
Bay Institute, San Joaquin Raptor Rescue Center, Friends of the River and
the Nor-Cal Fishing Guides and Sportsmen's Association.
"Karlton's decision was the correct one," said Zeke Grader, president of the
Pacific Coast Federation of Fishermen's Associations. "The Bureau is nuts
for going ahead with the contracts when the amount of water available is in
question. The Bureau should have done only 1 year renewals, when the water
available is uncertain, rather than locking in the contracts for 25 to 40
year."
"This ruling is enormously significant to the restoration of fish and
wildlife resources on the San Joaquin River and throughout California," said
Byron Leydecker, chair of Friends of the Trinity River and consultant to
California Trout. "The key issue here is what three agencies are consulting
on under ESA: the actual or the potential amount of water contracted."
The judge ruled that it must analyze the potential (full contract), while it
only analyzed the recent historical deliveries in the case of Friant.
"The implications of this are huge - imagine analyzing full contract
deliveries for San Luis Unit, with its huge drainage and selenium problems,"
explained Leydecker. "It's impossible to believe that the Fish and Wildlife
Service could reach a 'no jeopardy' conclusion under ESA with such a
scenario."
The potential is that many, if not all, of the contract renewal
consultations the federal agencies have done so far may have "authorized"
full contract deliveries while not analyzing the impacts of these
questionable deliveries. This ruling also throws into doubt the joint state
and federal plans to export more water from the Delta - which the signing of
the Central Valley Project contracts is based on.
It will be interesting to see how the Bureau and other agencies respond to
the decision. At press time, neither a spokesman from the Sacramento or
Fresno office of the Bureau of Reclamation was available for comment on the
court decision.
The massive Central Valley Project is the largest federal reclamation
project in the West. Congress enacted the Central Valley Project Improvement
Act (CVPIA) in 1992 to protect and restore Central Valley fish and wildlife,
including mandating the doubling of anadromous fish populations, yet many of
these species continue to decline.
"Fisheries agencies have used many of the same defective approaches when
considering other long-term contracts," said Hal Candee, NRDC senior
attorney. "Their inadequate approach fails to address how CVP operations
threaten the health of the entire bay delta ecosystem."
Faced with this precedent, I believe that the federal government should
immediately suspend all of the long term contacts already signed or in the
process of being signed in the Sacramento and San Joaquin Valleys until the
Bureau determines how much water is necessary for endangered fish.
When a judge determines that the federal agencies designated to protect fish
and wildlife have engaged in "arbitrary and capricious conduct," contracts
signed in violation of the law should be held invalid and not re-signed
until the exact impact upon salmon, steelhead, Delta smelt and other
endangered species by the Friant and other Central Valley projects is
determined. Natural science must upheld over political science - it's the
law!